Banting - status after the water leak in the roof (Solna)

Work is progressing after the water leak in the roof of the Banting dining hall. Scaffolding has now been built along the facade and roof work will be carried out.

The schedule looks like this:

  • Week 8: Establishment and erection of scaffolding
  • Week 9-10: Roof work
  • Week 11: De-establishment, cleaning and demolition of scaffolding

The schedule is set with some margin taking into account weather conditions and the work may be completed earlier.

As requested, two electric radiators have been ordered and will be installed, with hope that the temperature will be more comfortable in the dining hall.